In short
- Higher-risk materials such as most asbestos insulating board, pipe lagging and sprayed coatings must be removed by an HSE-licensed contractor, with at least 14 days' notice to the enforcing authority.
- Lower-risk materials such as asbestos cement and floor tiles are usually non-licensed work, but still need trained people and proper controls.
- Licensed removal ends with a four-stage clearance by an independent UKAS-accredited analyst.
- Asbestos is hazardous waste: ask for the consignment note.
Licensed or non-licensed?
The Control of Asbestos Regulations 2012 split work into three categories.
| Category | Typical materials | Who can do it | Key requirements |
|---|---|---|---|
| Licensed | Sprayed coatings, pipe and boiler lagging, most asbestos insulating board (AIB), loose-fill insulation | HSE-licensed contractor only | ASB5 notification at least 14 days before; enclosure; four-stage clearance |
| Notifiable non-licensed (NNLW) | Lower-risk materials that are degraded, or removed in a way that breaks them up | Trained, competent contractor | Notify before work starts; medical surveillance; records kept 40 years |
| Non-licensed | Asbestos cement in good condition, vinyl floor tiles, textured coatings in many cases, gaskets and bitumen products | Trained, competent contractor | Risk assessment, controls, correct waste disposal |
Our guide to licensed and non-licensed work goes into detail, including the short-duration rule for AIB.
What licensed removal involves
- Plan of work. The contractor writes a method statement covering the asbestos and every other risk.
- Notification. An ASB5 notification is sent to HSE or the local authority at least 14 days before work.
- Enclosure. The work area is sealed with polythene and kept under negative pressure, with an airlock and decontamination unit.
- Removal. Materials are wetted and removed with controlled methods, double-bagged and labelled.
- Clearance. An independent analyst carries out a four-stage clearance and issues a certificate for reoccupation before the enclosure comes down for good.
- Disposal. Waste goes in a sealed vehicle to a permitted site, with a hazardous waste consignment note.
HSE strongly recommends that the clearance analyst is appointed by the building owner or client, not by the removal contractor, so the check is independent.
Typical costs
Published 2026 guides put general removal at around £60 per square metre on average, encapsulation at around £30 per square metre, a single garage roof at £350 to £1,295 and a full asbestos garage at £1,100 to £3,750. Licensed jobs cost more because of enclosures, notification, decontamination and clearance. See the removal cost guide.
Before you book
- Make sure there is a survey or test result showing exactly what is being removed.
- For licensed work, check the contractor's licence on HSE's register.
- Agree who appoints the clearance analyst.
- Ask for the waste consignment note and clearance certificate to be sent to you.
Questions people ask
Can asbestos be left in place instead?
Often, yes. HSE guidance is that asbestos in good condition that is not going to be disturbed can be left and managed. Removal is needed when it is damaged or in the way of work.
What is encapsulation?
Sealing asbestos with a suitable coating or enclosing it so fibres cannot be released. It suits materials in reasonable condition that will not be disturbed, and is usually cheaper than removal, but the material stays and must be recorded and managed.
How long does licensed removal take to arrange?
The contractor must notify the enforcing authority at least 14 days before licensed work starts, so allow at least two to three weeks from instruction, plus the survey if one has not been done.
Do I need to move out?
For most domestic jobs the work area is sealed off and you can stay in the rest of the house. For larger licensed jobs the contractor may advise you to stay elsewhere until clearance.