In short
- Licensed: sprayed coatings, pipe and boiler lagging, loose-fill insulation and most work on asbestos insulating board (AIB). HSE licence, 14 days' notice, four-stage clearance.
- Notifiable non-licensed (NNLW): lower-risk materials that are degraded or broken up during work. Notification, medicals and records, but no licence.
- Non-licensed: bonded materials in good condition, such as asbestos cement and floor tiles removed whole, with proper controls.
- Short-duration work on AIB (no more than 1 hour per person in 7 days, 2 hours in total) can be non-licensed.
The three categories
| Licensed | Notifiable non-licensed (NNLW) | Non-licensed | |
|---|---|---|---|
| Typical materials | Sprayed coatings, lagging, loose fill, most AIB work | Lower-risk materials that are degraded or broken up during work | Bonded materials in good condition removed with minimal disturbance |
| Who | HSE licence holder | Trained, competent contractor | Trained, competent contractor |
| Notify | At least 14 days ahead (ASB5) | Before work starts | No |
| Medicals | At least every 2 years | At least every 3 years | No |
| Records | Yes, 40 years | Yes, 40 years | Not required |
| Clearance | Four-stage clearance by an independent analyst | Visual inspection; air testing where appropriate | Visual inspection |
How the decision is made
HSE's approach turns on four questions.
- Is the work sporadic and of low intensity? Short, occasional tasks, not continuous removal.
- Will exposure stay below the control limit of 0.1 fibres per cm³ over 4 hours?
- What is the material? Firmly bound materials such as asbestos cement behave very differently from friable ones such as lagging.
- What state is it in, and what will the work do to it? Removing a sheet whole is different from breaking it up.
If the work is not sporadic and low intensity, or exposure could exceed the control limit, it is licensed. Work on sprayed coatings, lagging and loose fill is licensed. Work on asbestos insulating board is licensed unless it is short-duration: no more than one hour for any one person in seven days, and no more than two hours in total for everyone.
Why it matters to you
- Programme. Licensed work cannot start until 14 days after notification, so allow for it.
- Cost. Licensed jobs carry fixed costs for enclosures, decontamination and clearance testing.
- Who you hire. A general builder cannot legally do licensed work. A licensed contractor can do all three categories.
Where to find more
HSE's guidance on licensed work, notifiable non-licensed work and non-licensed work, and the task sheets in Asbestos essentials (HSG210), set out the detail. Your surveyor's report should indicate the likely category for each material found.
Questions people ask
Is removing an asbestos garage roof licensed work?
Not normally. Removing asbestos cement sheets whole, with suitable controls, is non-licensed work. If the sheets are badly damaged or broken up during removal, it may become notifiable non-licensed work.
Is Artex removal licensed?
Usually not. Textured coatings contain a low proportion of chrysotile in a bonded matrix, so removal is generally non-licensed, and depending on the method and condition may be notifiable non-licensed work.
How do I check a contractor holds a licence?
HSE publishes a list of current licence holders. Ask the contractor for their licence details and check them on HSE's website.